WORK STATUS PVS FORTUNE ( 03-09-2010 )
Ø Structural work terrace room 100 % complete
Ø Structural work water tank and machine room 50% complete
Ø Ceiling plastering 1st to 14th floor 100% complete
Ø Masonry marking 14th floor 100% completed
Ø Masonry work ground to 9th floor 100% complete
Ø Masonry work 10th and 11th and 12th floor 80% complete
Ø Electrical work started, box fixing and pipe laying fourth floor B flat complete.
Ø Door frame fixing 4th floor completed.
Ø Door frame fixing 3trd floor 50% completed.
Ø Earth filling ground floor started.
Ø Parapet marking terrace floor started.
|