WORK PROGRESS REPORT - PEARL PARK SITE AS ON 03.09.2010
Block B
Structural work - Completed.
Masonry- Completed.
Inside plastering- Completed
External plastering - Completed
Electrical-Wiring completed, Cable laying and DB fixing completed
Plumbing-Internal line completed
Painting work
Primer work-3rd floor completed
External-2Side completed.
Tilling - Floor tilling almost completed, wall tilling (toilet) TF progress.
Block C
Structural work - Completed.
Masonry- Completed.
Inside plastering- 3rd floor almost completed
External plastering - almost completed
Electrical-Wiring 3rd completed, Cable laying and DB fixing at GF&FF floor completed, SF progress.
Plumbing-Internal line 3rd floor completed.
Painting work
Inside Primer work-2nd floor progress
Block D
Structural work- Completed
Masonry- 3rd floor almost completed
Inside plastering- 2nd floor completed
Electrical-, SF wiring completed, TF Wiring progress, DB fixing SF completed
Plumbing -SF & TF progress.
Block A
Structural work- Completed
Masonry- 2nd floor progress
Plastering- Ceiling TF progress, inside plastering GF progress
Electrical-Ceiling wiring TF completed